- Excuvation soil 2,500m3
- Reinforcement steel bars 250t
- Concreting of various complicated fundaments with (B20-B45) reinforced concrete in amount of 1000m3
- Volume of installed fabricated steel 300t
- Volume of installed equipmen on technological line 160t.
- Project cost 145 thousand EUR.