HeidelbergCement Group construction and assambling of cement terminal
Village Supsa, Lanchkhuti Region Kartuli Cementi HeidelbergCement Group, construction and assambling of cement terminal 2010-2011 – Excuvation soil 4500m3 – Reinforced steel bars 100t – Concreting of various complicated fundaments with (B-35) reinforced concrete in amount of 1200m3 – Volume of installed fabricated steel 130t – Rail way construction 190m long – Project cost 370 [...]
Assembling of fabricated steel for complex of GIMG hotel
Assembling of fabricated steel for complex of GIMG hotel (www.gimgbatumi.com) – Fabricated steel 600t – Project cost 188 thousand EUR
Construction of dividing pavement for highway by decorative borders of own production, Rustavi, Georgia 2010
- Project cost 105 thousend EUR
Kaspi cement plant, HeidelbergCement Group, Georgia 2009
- Assembling of cement plants’s III and IV cement mill filters’ technological line – Assembled fabricated steel 70t – Project cost 95 thousand EUR
Ready mix concrete plant, HeidelbergCementBeton Georgia, Tbilisi, Georgia, 2009
- Excuvation soil 2,500m3 – Reinforcement steel bars 100t – Concreting of various complicated fundaments with (B20-B45) reinforced concrete in amount of 2500m3 – Volume of installed fabricated steel 150t – Volume of installed equipmen on technological line 120t. – Project cost 113 thousand EUR.
Milled coal transportation line in Kartuli Cementi HeidelbergCement Group, Rustavi, Georgia 2008-2009
- Excuvation soil 2,500m3 – Reinforcement steel bars 250t – Concreting of various complicated fundaments with (B20-B45) reinforced concrete in amount of 1000m3 – Volume of installed fabricated steel 300t – Volume of installed equipmen on technological line 160t. – Project cost 145 thousand EUR.
Raw Dosing System in Kartuli Cementi HeidelbergCement Group, Georgia, 2009
- Excavation Soil 500m3 – Reinforced Steel Bars 12t. – Concreting of various complicated fundaments with (B20 – B45) reinforced concrete in amount of 250m3 – Volume of Installed Fabricated Steel 120t – Volume of installed equipment on technological line 50t.
Construction and Assembling of metallurgical plant GEOSTEEL LLC, Rustavi, Georgia, 2008-2009
- Excavation Soil 45,000 m3 – Reinforced Steel Bars 1,200 t. – Concreting of various complicated fundaments with (B20 – B45) reinforced concrete in amount of 12,000 m3 – Volume of Installed Fabricated Steel 3,000 t – Volume of installed equipment on technological line 1600 t.
Kartuli Cementi HeidelbergCement Group. Construction and assembling of clinker production plant’s new technological line, Rustavi, Georgia 2006-2008
Kartuli Cementi HeidelbergCement Group. Construction and assembling of clinker production plant’s new technological line, Rustavi, Georgia 2006-2008 – Excuvation Soil 70,000m3 – Reinforcement steel bars 2,200t – Concreting of various complicated fundaments with (B20 – B45) reinforced concrete in amount of 27,000m3 – Volume of erected fabricated steel 3,500t – Volume of installed equipments on [...]
Dismantling of Cement Plant in Germany
Kiefersfelden (Germany) Aug-Nov 2006 Complete dismantling and transportation in Georgia of HeidelberCement AG’s cement plant. – Clinker Burning Rotary Kiln (350t) – Raw Mill (180t) – Cement Mill (180t) – 120 containers of various dimensions, more than 3500t devices, equipments and technological lines.